Stop Chasing Vendor Quotes by Email
Picture a bid package that went out to six vendors two weeks ago. Quotes are due Friday. It's Wednesday, and someone on your team is digging through an inbox to work out who has responded, who asked for more time, and whether last night's revised quote replaces the first one or adds to it. Nobody can answer quickly, because the answer is spread across several people's email.
Why vendor quotes end up in email
Email is where RFQs start because it is easy. Everyone has it, vendors expect it, and sending a package takes a few minutes. The trouble is that sending is the simplest part of the process. After that you have to track who received the package, who plans to bid, what questions came back, what was clarified, and which version of each quote is current.
An inbox was never built to hold that information. It sorts by date, not by package or vendor. It belongs to one person, so the status of a bid lives with whoever happened to send it. A vendor's question may go to the project manager, the answer may come from the estimator, and the revised price may land with someone in procurement. Each person holds a piece, and nobody holds the whole picture.
Across more than 20 years of leading ERP implementations, M&A integrations, TSA separations and infrastructure projects, the lesson I keep coming back to is simple: work that has no visible owner and no shared status eventually gets done from memory. RFQs are a clear example.
What chasing quotes really costs
The obvious cost is time. Experienced people spend their days sending "just checking in" notes and rebuilding a status list that was accurate last week. But the larger costs show up later:
Thin competition. When no one notices a vendor has gone quiet until the deadline, you may end up with fewer real bids than you planned on, and little time to do anything about it.
Uneven information. If a clarification reaches only some bidders, the quotes you get back are priced against different assumptions.
Wrong versions. A superseded quote that makes it into the comparison can distort the decision, and it may not surface until after award.
Schedule slip. Late quotes push out the award, and a late award pushes on everything that depends on it.
Lost history. When someone leaves or moves to another job, the record of what was asked and answered can go with their mailbox.
None of these looks dramatic on the day it happens. It feels like ordinary project friction until a stakeholder asks why the award is late or why a scope item was priced two different ways.
What you can do this week
You don't need new software to get most of this under control. Start with your next open bid package:
Name one owner per package. One person is responsible for status, even if others handle the technical questions.
Build a simple RFQ log. One row per vendor: date sent, intent to bid, questions open, quote received, current version, follow-up date.
Ask for intent to bid early. A clear yes or no a few days after issue tells you whether you need to invite someone else while there is still time.
Set follow-ups before the deadline. Decide your check-in dates when the package goes out, so reminders don't depend on someone remembering.
Send every clarification to every bidder. Number them, and ask vendors to confirm which ones their quote includes.
Use a shared mailbox and a naming rule. Package, vendor, revision and date in every file name makes the current quote easy to find.
Review the log for ten minutes in your weekly project meeting. The habit matters more than the tool.
Where Projexus fits
Projexus was designed by project and program management practitioners, and this is one of the problems it was built to take off the team's plate. With vendor requests (RFQ), you send requests, track responses and compare quotes in one place, so status no longer depends on whose inbox you search.
The bid register, with AI-assisted evaluation, lets you compare quotes side by side and flag gaps before award. And because opportunities, bids and jobs sit in one place, bidding stays connected to the project that follows.
You don't have to change everything at once. Teams can start with the bid register, risks and cost tracking and grow from there. Projexus is currently in an invite-only pilot, and pilot partners get hands-on setup and a direct line to the team that builds it.
Tomorrow, we'll look at AI-assisted bid evaluation: what it should do, what it shouldn't, and why people still make the award decision.